The trustees at Chiddingstone Castle had an ambition to bring the orangery, a simple mock gothic ‘ruin’, back into service. Because it is only partially enclosed, the intention was to turn it into an external wedding venue. With an existing Grade I listed structure of questionable structural integrity, it was necessary to find a solution that limited the loads transferred to it.
The gridshell roof from above
Cable and clamp testing in our yard
Testing lathe to destruction and finger joint failure
The node clamp at the intersection of the lathe
Buro Happold carried out the conceptual engineering prior to our involvement. Essentially, the structure comprises an elliptical rigid ring beam of ply, sandwiched with steel plate, supporting a lattice of chestnut lathe.
The ring beam ‘sandwich’ being fabricated
A system of cables, anchored to the ring beam and running through the node clamps, provides triangulation to the structure.
The chestnut grid is constructed with four layers of lathe sandwiched together with blocking pieces that enable them to cross at the nodes. Each lathe is 40mm wide by 35mm deep and up to 12 metres long.
The four layers of lathe clearly visible
The apron brackets secured to the ring beam
The ply apron being fabricated
Erection on site was carried out within a tented structural scaffolding by TR Services (Bristol) Ltd. With the ring beam constructed and sitting on stools on the scaffold floor, the lathes were laid out as a flat lattice with the connecting nodes loose. The lattice was then lifted into shape over a number of days, allowing the lathes to slide through the nodes and shape to the required form. High ambient temperatures and low humidity were drying the lathe quicker than anticipated so this was counteracted by regular wetting down. Once the form had been achieved, the nodes were tightened and the cables secured around the apron.
The gridshell is levelled on stools to ensure accurate construction
The lathe being lifted into shape over the ring beam
The former from underneath
The scaffold floor was then removed and the roof structure lowered onto the steel stanchions that transfer the load to the new raft foundation under the stone floor.
The gridshell sitting on its supporting stanchions
Copyright © 1993–2008 Carpenter Oak & Woodland Limited · site map · legal notices · accessibility |